CQV Decision Lab — BRX-301: The Qualification Challenge
- Briefing
- OQ response
- Investigation
- Recovery
- Ad hoc meeting
- Contingency follow-up
- Release gates
- Debrief
Simulated choices are not real authorizations.
Briefing
Briefing
Fictional training scenario. Not validated GMP software and cannot authorize real manufacturing.
You are the CQV Project Lead for DemoCo Biologics. BRX-301 is a 2,000 L single-use bioreactor. The campaign target is Week 11. Manufacturing can accept a move through Week 14. The reference recovery in the case study is Week 12.
OQ agitation challenge OQ-AGT-07 is set at 150 rpm. The acceptance band is 142.5–157.5 rpm. The result is 163 rpm, outside the band. Alarm AUT-017 sounds on the skid and does not appear on the DCS-01 summary. Protocol discrepancy PD-BRX-002 is the record for the failure. BRX-301 is not released for GMP use.
Synthetic demonstration. Fictional people, equipment and data. Not a validated GxP system and not client work.